Service

Civil & Structural Works

Structural works are run by our own site engineer with documented method statements, bar bending schedules and pour cards. Steel, formwork and cover are checked and signed off before concrete is called.

All services
Double-layer reinforcement mesh inside a waterproofed water tank structure
Double-layer mesh and wall starters fixed inside a waterproofed tank before slab casting.
Column formwork with tie bars, cover blocks and props
Column formwork: tie bars, spacers and props inspected for line, plumb and cover.
Slump cone test being carried out on fresh concrete at site
Fresh-concrete slump test recorded on the pour card at the point of delivery.

Scope of works

  • Method statements, shop drawings and bar bending schedules
  • Formwork design, erection, propping and de-shuttering programme
  • Steel fixing with certified spacers and lap lengths
  • Concrete placing, compaction and curing regime
  • Blockwork, plaster and structural repairs

Engineering detail

Standards we work to

Slump control
Target 100–180 mm depending on element and pump distance
Concrete temperature
Kept below 32 °C at placing; ice/chilled water in summer
Cube testing
7 and 28-day cubes per pour, results filed with the pour card
Curing
Minimum 7 days continuous curing / curing compound on slabs

Related services

Need civil & structural works on your project?

Send us your drawings or scope and we will price it line by line, with a named engineer for your site.